1990 – 1993 Sleipner R Temp. Phase (Statoil)

1989 – 1993 Sleipner A & R (Statoil)

1993 – 1996 Sleipner T & B (Statoil)

1995 – 1996 Sleipner B Temp. Phase (Statoil)

1996 – 1998 Åsgard A (Statoil)

1997 – 1998 Åsgard C (Statoil)

1998-2000 Åsgard B (Statoil)

2000 Huldra (Statoil)

2000 Statoil VOC

  • Systems verification
  • Hazop
  • Plant testing procedures

2000 – 2001 Pipeline RFO (Ready for Operation) Hazops (IKM)

2001 – 2003 Kristin Topside and Sub Sea (Statoil)

2001 – 2003 Sleipner T Amine Task Force (Statoil)

  • Trouble shooting of SLT Amine PLant.

2004 – 2008 Snøhvit LNG Plant (Statoil)

2009 – 2010 Snorre B Task Force (Statoil)

  • Debottleneck study of Snorre B process plant.

2008 – 2012 Valhall VRD (BP)

  • Web database solutions for procedures (SATOS)
  • Web database solutions for Material Handling
  • Translation and implementation of material handling procedures
  • Start-up preparations task force
  • Updating of commissioning procedures for offshore commissioning of process systems.

2011 – 2016 Goliat (ENI)

2013-2015 Edvard Grieg (Lundin)

2014 Gullfaks (Statoil)

2014 Aasgard (Statoil)

2014 – Clair Ridge (BP)

2014 – Glen Lyon (BP)

2015-2017 Mariner A (Statoil UK)

2016-2017 Hilli FLNG (Golar)

2017- Johan Sverdrup (Statoil)